This California Department of Transportation
(Caltrans) project entailed seismic retrofitting of all overpass bridges
along a stretch of Freeway 101. Each bridge was lifted off its foundation
and placed on seismic pads specially designed to withstand the lateral
and upward loads resulting from seismic activity acting on the bridge
assembly during an earthquake. To provide additional strength and
rigidity, once the seismic pads had been successfully installed, metal
plates were wrapped around the columns followed by the application
of concrete. As the column work proceeded, the work sequencing refocused
its efforts on repairing and refinishing all concrete which had become
damaged. The abutments were reinforced as well as every column on
each bridge.
DACM
Project Management became involved with the project as a
result of Caltrans' desire to determine and evaluate the actual manhours
that the contractor was expending at each bridge location. To provide
this information, it was determined that we would prepare a productivity
analysis. As a basis for the conclusions which DACM
Project Management would reach through the analysis, Caltrans
provided our engineers with copies of the projects resident engineer's
and inspectors daily reports. By evaluating the reported manhours
and assigning them logically to construction activities, We could
establish the work effort expended at each bridge and could extrapolate
roughly from this information, the contractor's and subcontractor's
costs for each task or phase as well as the total cost to perform
the work at each bridge site.
